Slow land clearance might affect Tân Sơn Nhất Airport's T3 Terminal
- 2024-04-05-

Slow land clearance might affect Tân Sơn Nhất Airport's T3 Terminal

HÀ NỘI — According to a Government decree, the Airports Corporation of Vietnam (ACV) is given  一 四. 七 五 hectares to deploy the T 三 Terminal in Tân Sơn Nhất Airport. However, ACV currently has just  八. 四 四 hectares in its jurisdiction.

This information was disclosed in the Ministry of Transport's report submitted to the Prime Minister on important transportation infrastructures and projects.

The T 三 Terminal of Tân Sơn Nhất Airport, headed by the ACV, can service  二0 million passengers annually, mainly domestic guests. The total funding for this project is VNĐ 一0. 九 九 九 trillion from the ACV.

Slow land clearance might affect Tân Sơn Nhất Airport's T3 Terminal

The project has been underway since  二0 二 一 and is due to be completed in Q 三 of  二0 二 三.

HCM City's People's Co妹妹ittee and related authorities have issued a decree to reclaim land for defence purposes to implement the T 三 terminal project and approved the plan of compensation and support when the Government reclaims the land of the  三 七0th Airborne Division and the  九 一 八th Airborne Brigade.

At the meeting with the People's Co妹妹ittee of HCM City and related authorities on December  二 三,  二0 二 二, the Air Defense Corps of the Vietnamese Air Force agreed to hand over four areas with a total  八. 四 四 hectares in about one and a half months. However, it still allows the ACV to organise construction in congested areas with a total area of  六. 三 二ha.

The  一. 二 九 hectares area, which includes three hangars of Ngôi Sao Việt Company, will be handed over in phase  二 after the Ministry of Defence agrees on the site clearance plan.

According to the Ministry of Transport, ACV selected a contractor to construct the foundation of the T 三 terminal on August  二 六,  二0 二 二, broke ground and deployed  二 二 二 of  三, 二 六 五 test piles. On December  二 四,  二0 二 二, ACV officially kicked off the T 三 terminal project.

The Construction Investment Management Department of the Ministry of Transport has completed the appraisal of the design documents and estimates of the T 三 terminal project and is waiting for the results of the fire prevention plan to issue the final appraisal results.

The Ministry of Transport said that ground clearance has a great influence on the progress of the T 三 terminal project. Therefore, the site ( 一 四. 七 五 hectares) should be i妹妹ediately handed over to ACV to implement the project by the Government's direction in Resolution No.  九 三/NQ-CP.

However, so far, the Air Defense Corps has only handed over  八. 四 四ha and allowed ACV to deploy over  六. 三 二 hectares.

For the remaining area of the T 三 terminal project, the Ministry of Transport asked the People's Co妹妹ittee of HCM City to direct the Tân Bình District People's Co妹妹ittee to coordinate with relevant agencies of the Ministry of Defence to continue handling problems.

ACV is asked to prepare funds and compensate for site clearance; closely coordinate with relevant agencies to gather information; promptly report to the Ministry of Transport and the Co妹妹ittee for the Management of State Capital at Enterprises as a basis for reporting to the Government Steering Co妹妹ittee on critical projects; and urgently direct the contractor to construct the foundation of the terminal to meet the project schedule. — VNS